SELC releases new analysis of Bypass plan, questions impact on traffic

An analysis released today of previous traffic studies for the proposed Route 29 bypass in Albemarle County confirms that the highway will not solve traffic congestion on Route 29, and urges federal and state transportation officials to focus on alternative solutions.

PRESS RELEASE: Southern Environmental Law Center–– An analysis released today of previous traffic studies for the proposed Route 29 bypass in Albemarle County confirms that the highway will not solve traffic congestion on Route 29, and urges federal and state transportation officials to focus on alternative solutions.

The report was written by Norm Marshall, a traffic expert with Smart Mobility, Inc., a consulting firm specializing in transportation modeling, design and planning, and was released by the Southern Environmental Law Center, which is sending the report to the Federal Highway Administration, Virginia Department of Transportation, Albemarle County Board of Supervisors, Charlottesville City Council, and others.

Read the report (pdf) here: http://selc.southernenvironment.org/site/R?i=2Ja69UmF3fgjoAjXMT5l0w

While finding flaws in the studies, Marshall says that the most thorough one, done between 1988 and 1990, indicated that the bypass would not remove enough vehicles from Route 29 to improve traffic congestion significantly. That study found that only about 10% of the traffic on the most congested section of Route 29 is "through" traffic — in other words, the vast majority of vehicles are shoppers, workers and residents making local trips. The data indicated that because of this, the amount of traffic diverted onto the bypass would still leave Route 29 operating at a failing level of service during peak periods.

Marshall also finds that increased traffic from development approved north of the bypass in recent years would significantly reduce any minimal traffic relief the bypass might offer.

"The proposed bypass would be even less effective today than the limited value demonstrated by the 1988-1990 modeling because of intensive development, large traffic volumes, and the increase in the number of traffic signals north of the proposed terminus of the project," he writes.

Since 2003, in Albemarle County alone, roughly 3,000 residential units and more than 3 million square feet of other development have been approved north of where the proposed bypass would tie back into Route 29. In addition, there are nine traffic lights on the 5.7-mile stretch of Route 29 in Albemarle County north of the bypass, and at least three more are proposed.

Marshall also finds that the studies on which VDOT based its most recent traffic projections have serious flaws. As a result, VDOT’s forecasts of the number of vehicles that would use the bypass, including the estimate in its Request for Proposals (RFP) for the project, are completely off base. These forecasts appear to be
based on an unrealistic annual rate of traffic growth of 1.7%.

In fact, the actual rate over the past two decades on Route 29 between Rio and Hydraulic roads, the busiest segment of the corridor, has beenonly 0.5%, and traffic has actually dropped in this stretch in thelast ten years, according to the report. Using this 0.5% rate of growth, it would be the year 2230 before 32,300 vehicles per day traveled the bypass.

"VDOT’s sky-high projection of traffic growth results in an unjustifiable estimate of the number of vehicles that would use the bypass, and hides the truth that it is an outdated and ineffective proposal," said Morgan Butler, Director of SELC’s
Charlottesville-Albemarle Project.

The report identifies key steps FHWA and VDOT must take to develop a valid traffic forecast that presents a realistic picture of any benefits of the proposed bypass. Marshall recommends that the agencies examine a combination of improvements — including grade-separated intersections on Route 29, which have been shown to be
more effective in reducing delay on Route 29 — and enhancements to the local road network, as recommended in a recent study prepared for the Thomas Jefferson Planning District Commission.

"The amount of money that would be necessary to build the proposed bypass could be spent much more effectively on targeted improvements along the Route 29 corridor," Marshall concluded.

****************************
The Southern Environmental Law Center is a regional conservation organization using the power of the law to protect the health and environment of the Southeast (Virginia, Tennessee, North and South Carolina, Georgia, and Alabama). Founded in 1986, SELC’s team of 40 legal experts represent more than 100 partner groups on issues of climate change and energy, air and water quality, forests, the coast and wetlands, transportation, and land use.
 