Head to head: Feds approve controversial pipelines

Though the Federal Energy Regulatory Commission approved the Atlantic Coast Pipeline October 13, those opposing the $6 billion and 600-mile gas fracking project say they’re not going down without a fight.

“It’s not over by any means,” says Kirk Bowers, a program coordinator with the local chapter of the Sierra Club. Though he’s not showing his hand, he says his organization recently changed its policy against participating in civil disobedience and training sessions have been popping up across the commonwealth.

FERC also just approved the Mountain Valley Pipeline in southwest Virginia, where Bowers says opponents have blocked roads with their bodies, vehicles and gates to prevent surveyors from entering their properties.

In the case of the Atlantic Coast Pipeline, he says environmental groups and their attorneys have 30 days to file appeals. And they will.

Dominion Energy sent out a press release late Friday night that the ACP had been issued a Certificate of Public Convenience and Necessity from FERC—the most significant milestone for the project yet, it said.

“Our public utility customers are depending on this infrastructure to generate cleaner electricity, heat homes and power local businesses,” says Leslie Hartz, Dominion’s vice president of engineering and construction, who says the project will result in lower energy costs and a cleaner environment, because the ACP will replace coal-burning power plants.

FERC chair Cheryl LaFleur dissented in the approval, and said the project isn’t in the public’s best interest, but noted that utility customers in Virginia and North Carolina have already subscribed to 90 percent of the pipeline’s natural gas capacity.

To proceed with construction, Dominion still needs water permits from the states in which the pipeline will run—West Virginia, Virginia and North Carolina.

In West Virginia, where Dominion first asked the Department of Environmental Quality for the water permit, which it was granted, legal group Appalachian Mountain Advocates filed suit—and won—this summer. Now, the energy giant has to go back to the drawing board, according to Bowers, who says Virginia water permit hearings are slated to take place in Richmond in December.

Last week, the Sierra Club filed an appeal with the State Corporation Commission, Bowers says, because Dominion has allegedly contracted the ACP’s gas to its own affiliates without the SCC’s permission, which is required in Virginia.

In early September, anti-pipeline group Bold Alliance filed a property rights lawsuit against FERC, alleging the abuse of eminent domain for private gain.

Dominion has maintained it would only use eminent domain as a last resort. It also asserts that the ACP has undergone 300 route adjustments and one of the most thorough environmental reviews for a project of its scope.

“This unprecedented scrutiny should give assurance to all communities that their voices have been heard and that the project will be built in a way that protects public safety and the environment,” Hartz says.

Nelson County resident and affected landowner Richard Averitt is among 50 plaintiffs in the Bold Alliance suit.

“Hundreds of landowners have stood strong and have refused to negotiate with the pipeline companies,” he says. “We have vowed to fight to protect and defend what is constitutionally ours, and we will win.”

Categories
News

Impact study: Pipeline nears approval, opponents fire back

The Federal Energy Regulatory Commission released its final environmental impact statement for the Atlantic Coast Pipeline July 21, and it said the proposed 600-mile, $5.5 billion natural gas pipeline will have a “less than significant” impact on the environment.

“The [final environmental impact statement] paints a terrifying picture of a bleak future,” says Ernie Reed, the president of anti-pipeline group Friends of Nelson.

According to Reed, the ACP will eliminate almost 5,000 acres of interior forest habitat and destroy 200 acres of national forests and nearly 2,000 waterbody crossings along its path from West Virginia to North Carolina. “And all this to give Dominion and Duke Energy enough gas to burn our way into hell,” he adds.

Dominion Energy and Duke Energy are the major companies backing the ACP.

Also on July 21, the U.S. Forest Service released a draft of the record of decision, which said the ACP “can be implemented with limited adverse impacts,” and, in its final form, will authorize the use and occupancy of National Forest System land for the ACP through the George Washington and Monongahela national forests.

Environmentalists allege that the documents fail to depict the pipeline’s true effects, and that some biological evaluations, road analyses and consultation with the U.S. Fish and Wildlife Service are incomplete.

“It is interesting that this decision was made by the regional foresters in offices hundreds of miles away from these forests,” says Reed. “No one who has stepped foot in these forests could ever come to such a delusional conclusion.”

FERC found that the ACP could negatively impact seven endangered species: the Indiana bat, northern long-eared bat, Roanoke logperch, Madison Cave isopod, clubshell mussel, running buffalo clover and small whorled pogonia.

“It is outrageous that the Forest Service would sign off on a scheme like this with the full knowledge that it will harm endangered species,” says Misty Boos, executive director of environmental group Wild Virginia, which has also been vocal in its opposition to the pipeline.

She says FERC’s final environmental impact statement and the Forest Service’s record of decisions “make it clear that we cannot rely on the federal government to protect our forests and drinking water,” and that the Virginia Department of Environmental Quality has the authority to reverse the two groups’ decisions.

“All eyes are on the DEQ in the coming weeks,” Boos says. “They must do what the feds have not and choose our safety over private profits.”

Wild Virginia will submit a formal objection to the draft record of decision, and “litigation is certain to follow,” according to a press release.

Dominion continues to assert that its pipeline will be safe for all.

“Over the last three years, we’ve taken unprecedented steps to protect environmental resources and minimize impacts on landowners,” says Leslie Hartz, Dominion Energy’s vice president of engineering and construction. She says her team has made more than 300 route adjustments to avoid environmentally sensitive areas. “In many areas of the project, we’ve adopted some of the most protective construction methods that have ever been used by the industry.”

Construction on the pipeline could begin by the end of the year, according to Dominion.